Construction Notice:
- South of 4th Street: Construction crews will be finishing up construction work in this area.
- 6th Street to 8th Street: Crews will be working on final grading in the railroad right-of-way on weekdays during normal working hours.
- 11th Street: Crews will install permanent cable railing to enhance safety around a drainage ditch in the railroad right-of-way through the end of the month.
- 12th Street to Coast Blvd: Crews will be working on completing drainage ditches and final grading in the railroad right-of-way on weekdays during normal working hours.
- Beach: Periodic work near the seawalls along the project area will continue through summer 2026. Planting, revegetation of affected slopes, and temporary irrigation installation are ongoing.
- Sea Cliff Park: The southern section is closed until the end of August for construction.
Construction schedules are subject to change. (updated 07.23.2026)
Project Overview
Stabilization of the Del Mar bluffs is an ongoing, multiphase effort to maintain safe, stable, and reliable train tracks through this stretch of the LOSSAN Corridor. Our goals are to increase safety and service reliability and minimize the chances of track damage due to bluff retreat and seismic events. We accomplish this by installing supports and directing stormwater runoff. To ensure the long-term viability of the corridor, SANDAG is evaluating alternative strategies to relocate the tracks completely off the bluffs.
Schedule
Since 2003, SANDAG and the North County Transit District (NCTD) have completed four stabilization projects between Coast Boulevard and Torrey Pines State Beach. These projects included the installation of more than 230 support columns and investment in drainage infrastructure.
Phase 4
Phase 4 construction occurred between May 2020 and January 2021 and included the installation of additional support columns, construction of a drainage channel on top of the bluffs, repair of drainage infrastructure, and stabilization of existing headwalls.
Phase 5
In spring 2024, we began Phase 5 stabilization efforts. More support columns and drainage improvements will be added, along with new retaining walls, erosion control measures, and native plants. These efforts are critical to protect the bluffs in the event of earthquakes, large storms, and sea level rise.
Find construction updates and other updates on our news page.
Phase 5 Del Mar Bluffs Stabilization Map showing stabilization efforts, new sea walls and construction staging areas.
Budget
Phase 5 will cost roughly $88 million and is funded through a combination of state, federal, and local sources.
Connect with Us
For more information, contact the SANDAG LOSSAN project team at lossancorridor@sandag.org or call our hotline at 858.549.RAIL (7245).

