Del Mar bluffs Preparatory work commenced in late May 2007. Pile installation, a process where large metal columns are placed underground to stabilize the area, commenced late June 2007 beginning at the northern end of the project near Ocean Avenue and then proceeding south to 8th Street and then on to Anderson Canyon near Torrey Pines State Beach. Additional retaining wall work followed proceeding in the opposite direction of how the piles were installed. Work appears to be ahead of schedule and is anticipated to be completed in late 2007. The most significant portion of the work is required to take place from approximately 10 p.m. to 5 a.m., Sunday through Thursday evenings, when rail service is suspended. For more information, contact Ramon Ruelas, Project Manager, at (619) 699-6944 or rrue@sandag.org. If you would like to receive information regarding this project as it becomes available, please send an e-mail to pio@sandag.org with ‘Del Mar Bluffs Project’ in the subject line and you will added to our e-mail distribution list. Information also is available by visiting www.sandag.org/delmarbluffs. Project Manager: |